World Bank's $375.9m grid project awaits loan agreement, zero disbursed

By Editorial Desk2 min read
World Bank's $375.9m grid project awaits loan agreement, zero disbursed
Both financing components are classified as not effective and no money has been disbursed, with the loan awaiting a Subsidiary Loan Agreement between the Ministry of Finance and the National Grid Company.

Pakistan's $375.9 million World Bank-funded Grid Stability Enhancement Project has yet to become effective, and no money has been disbursed. The financing agreement is signed, but the loan only takes effect once the Ministry of Finance and the implementing entity, the National Grid Company of Pakistan, sign a Subsidiary Loan Agreement. Until then, key procurement activities are still awaiting commencement.

The World Bank's latest Implementation Status and Results Report rates progress towards the project's development objectives and overall implementation progress as "Moderately Satisfactory". Both financing components — a $200 million IBRD loan and $175.9 million in IDA financing — are classified as not effective, with zero disbursements recorded. Overall implementation risk is rated "Substantial", and political and governance risks are classified as "High". Macroeconomic conditions, sector strategies and policies, and institutional capacity for implementation and sustainability are also rated substantial risks.

Approved on July 9, 2026, the project targets lifting use of the South-Central High Voltage Direct Current transmission line from 2,000 megawatts to 4,000MW by July 2029. It aims to raise southern region renewable capacity enabled through the transmission network from 12,720 MW to 13,831 MW, cut the five-year annual average Energy Not Served from 60 gigawatt-hours to 45GWh by December 2029, and enable $447 million in private capital through renewable energy investments by July 2029.

On the ground, the plan involves Static Synchronous Compensators at three substations — 800,000 KVA each at R.Y. Khan and Dadu and 400,000 KVA at Guddu — plus switched shunt capacitors totalling 1.632 million KVA at 17 substations and shunt reactors totalling 1.132 million KVA at nine. Restructuring the former National Transmission and Despatch Company so its successor entities operate on commercially oriented principles by June 2029 is also envisaged, but that implementation plan remains unformulated and unapproved, with March 2027 set as the target for adoption.

Preparation work supported by the Grid Financing and Preparation Project grant is already under way, and that grant was recently extended by six months. The project sits within the broader BEST-PAK Multi-Phase Programme, is implemented by the Ministry of Energy's Power Division and the National Grid Company of Pakistan, and carries a closing date of December 31, 2029. It also targets lifting women's representation in technical and managerial positions at NGC from 10 percent to 18 percent by July 2029 and establishing childcare support by December 2027.